Atlassian is changing how automation is measured in Jira, Confluence and its other cloud apps: usage is now counted in steps rather than rule runs. Usage-based billing starts on 3 December 2026. Since 5 November 2026, runs that perform no actions are no longer counted.
What exactly is changing
A new unit, the step. Atlassian defines a step as a single executed part of an automation flow. Counting follows precise rules:
- Trigger: one step per run. A condition set inside the trigger adds no step.
- Condition: one step per executed condition, even with several criteria. A condition that evaluates to false also counts, unless no actions run.
- Action: one step each time it runs.
- Branch: one step for the branch, plus the steps in the path that actually runs. Unused paths cost nothing.
- Loop: one step for the loop, plus the steps inside it for each item processed.
Atlassian gives examples: a trigger, a separate condition and an action make 3 steps, and only 2 if the condition moves into the trigger. A loop running three times with one action each time makes 5 steps.
What does not count. Some system steps (logging, creating a variable or a lookup table, re-fetching work item data, looking up work items), aborted or throttled runs, failures caused by Atlassian-side errors and, since 5 November 2026, runs with the status “NO_ACTIONS_PERFORMED”. The “Use Rovo”, “Use agent” and “Use Jira Coding agent” steps consume Rovo credits, not steps. Third-party AI actions, however, such as “Use Cursor” or “Use GitHub Copilot”, do count as steps.
A shared allowance. The monthly allowance is pooled at organisation level: Jira, Confluence, Jira Service Management, Jira Product Discovery and Teamwork Collection all draw from the same total. It depends on subscriptions and plans. For example, Atlassian’s page lists, per user per month, 400 steps for Jira Standard, 750 for Premium and 1,000 for Enterprise, and 100, 250 and 500 steps for Confluence on the same plans. Free plans receive a fixed amount per subscription.
No more unlimited Enterprise. Enterprise plans no longer have unlimited automation and also receive an allowance.
Overage and stops. Extra steps cost $0.50 per 1,000, billed on the next invoice. Prepaid packs are also available. Admins are notified at 80% and 100% of usage and can set monthly limits. If extra usage is switched off and the allowance runs out, new flows stop until it refreshes; flows already in progress complete, manual triggers are paused too, and events that occur during the pause are neither stored nor replayed. There is no way to mark a flow as a priority.
The context
Until now, Atlassian counted successful runs: one completed flow was one run, however many actions it contained. Limits were set per app and per plan, and Enterprise customers had no cap. The new model measures each flow in detail and pools allowances at organisation level. What stays the same, according to Atlassian: automation remains included in the subscription, existing flows are unchanged and the allowance refreshes every month.
What it means for project teams
- Project manager: the automations the project relies on (transitions, assignments, notifications) can stop if the allowance runs out and extra usage is off. That risk deserves a line in the risk register.
- PMO: because the allowance is shared, a heavily automated project uses up capacity for the others. Usage tracking becomes a portfolio matter.
- Jira admin: usage can be checked in Atlassian Administration (Usage, then Meters, then Automation steps), in Jira (Settings, System, Global automation, Usage) and in Confluence. Each flow leads to its audit log, showing steps per run. Rule design now has a cost.
- Leadership: automation becomes a variable cost line. A policy is needed: a cap, prepaid packs or a hard stop.
What I take from this for your projects
- Measure before 3 December. Check the allowance, usage and forecast in Atlassian Administration, and identify the flows that use the most steps.
- Optimise the design. Put conditions inside the trigger where possible, watch loops that multiply steps by the number of items, and space out scheduled flows that run more often than needed.
- Identify critical flows. Since no flow can be marked as a priority, list the ones your processes depend on and simplify secondary flows to free up capacity.
- Decide on an overage policy. Choose between a monthly limit, packs or a hard stop, bearing in mind that a stop pauses flows and missed events are not replayed.
- Track Rovo credits separately. Atlassian’s AI steps draw on Rovo credits, while third-party AI actions use steps. Both budgets need tracking.
Prices and allowances can change: check Atlassian’s pages before setting a budget.
Want to review your automation rules before this deadline? Get in touch.