Since 30 March 2026, Atlassian no longer sells Data Center licences to new customers. This is the first step of the timeline announced on 8 September 2025 as part of the Atlassian Ascend programme, which leads to the end of life of Data Center products on 28 March 2029. Existing customers can still buy and expand licences until 30 March 2028.
What changes exactly
Atlassian has set a four-date timeline, with each change taking effect at 23:59 Pacific Time:
- 16 December 2025: the Marketplace no longer accepts new Data Center app submissions.
- 30 March 2026: new customers can no longer buy or request a quote for the affected Data Center products, or for associated Data Center apps.
- 30 March 2028: existing customers can no longer buy Data Center products, new apps or licence expansions.
- 28 March 2029: end of life. Data Center licences and associated app licences expire, and the products become read-only.
The products concerned are Jira Software Data Center, Jira Service Management Data Center, Confluence Data Center, Crowd Data Center, the Data Center mobile apps, and both Atlassian and third-party Data Center apps on the Marketplace. For a new customer, cloud is therefore now the only option for Jira, Confluence and Jira Service Management.
There are exceptions. Bitbucket Data Center and Bamboo Data Center are not affected by end of life and will continue beyond 2029; their existing customers get access to a Bitbucket Hybrid Licence covering Bitbucket Data Center, Bamboo Data Center and Bitbucket Cloud. Jira Align Data Center is not included either.
For existing customers, nothing stops immediately. Renewals remain possible after 30 March 2026, but cannot extend beyond 28 March 2029: a 12-month renewal that would go past that date is prorated. Until then, Atlassian continues to provide technical support, security fixes for critical vulnerabilities and connectors to cloud. Extended maintenance may be granted beyond that date, but only by exception and at an additional cost. Atlassian also points out that, to deliver these security fixes, it may ship other updates, such as platform fixes or support for new browsers.
If no plan has been agreed with Atlassian by then, the licence expires on 28 March 2029 at 23:59 Pacific Time and the environment becomes read-only: the products can no longer be used, although the data remains available in read-only mode.
The context
Atlassian explains the decision through a firmly cloud-first strategy. The vendor states that 99% of its more than 300,000 customers already use its cloud, and that 75% of its most complex and regulated customers are on a path to cloud. It highlights cloud sites supporting 150,000 users on Confluence and 100,000 on Jira, and says it is building FedRAMP High and Impact Level 5 environments ahead of Data Center end of life.
To support the transition, Atlassian offers self-service tools for organisations with fewer than 1,000 users, the free FastShift programme above 1,000 users, which the vendor says cuts a migration from 12–16 months to 2–6 months, and dedicated support (Solution Design Acceleration) above 5,000 users.
On the Marketplace side, Atlassian asks app vendors to communicate proactively with customers about migration plans and to invest in migration pathways.
What it means for project teams
- Project manager: a cloud migration becomes a dated project with a non-negotiable deadline. Scoping should start from 28 March 2029 and plan backwards, keeping 30 March 2028 in mind for any licence expansion needed before then.
- PMO: in a portfolio with several instances, migrations need sequencing, resources need reserving and dependencies with other projects need tracking. Prorated renewals also affect the budget.
- Jira administrator: the Marketplace app inventory becomes critical. Each app needs a cloud equivalent, an alternative or a decision to drop it, and workflows, fields and automations must be checked one by one.
- Senior management: the choice is no longer whether to stay or leave for Jira, Confluence and Jira Service Management. It is about timing, budget, and the compliance or data residency requirements to check on the cloud side.
What I take from this for your projects
- Start with the inventory: list instances, projects, spaces, apps, integrations and volumes. It is the basis for any serious estimate.
- Decide on apps early: for each Marketplace app, check whether a cloud version exists and ask the vendor about its migration plan.
- Check your scope: if you use Bitbucket or Bamboo Data Center, the situation is different; do not put them on the same timeline by default.
- Refine the method on a low-risk scope: start with low-stakes projects and spaces to test the tools, measure durations and adjust.
- Involve the business: workflows and habits sometimes change; user acceptance testing and change management are part of the project, not an afterthought.
- Do not count on extended maintenance: it is reserved for exceptions and comes at a cost. A plan that works without it is safer.
Need to plan your exit from Data Center? Let’s talk.